The future Valley Animal Hospital!

Valley Animal Hospital after renovation

 

 

 

Our General Contractor

D. Baker & Co.

 

 

Our Architect

A & E International

 

 

The Designer of Our Rainforest Skylight

 

 

 

The Finished Product, Valley Animal Hospital, October 6, 2000

The Finished Product, October 6, 2000

 

 

 

September 30, 2000

September 30, 2000  New paving, outside stucco almost finished, new fence installed, most interior details finished.  And yes, the skylight is IN!!!!

 

 

 

 

 

September 9, 2000

September 9, 2000  Move completed to new addition. Renovation commences on existing building exterior.

 

 

 

 

August 11, 2000

August 11, 2000  Steps and side paving installed.  Lots of internal changes.  Remodeling starts on the existing building.  Now if only that skylight would get here.

 

 

 

July 7, 2000

July 7, 2000  What a difference.  It actually looks like the drawing.  External stucco of new addition finished. Windows and doors installled.

 

 

 

 

June 23, 2000June 23, 2000  Stucco base coat almost finished.  Color coat started.  Interior drywall hung.

 

 

 

 

June 16, 2000June 16, 2000 Stucco started.  Door arches finished.  Permanent roof installed.

 

 

 

 

June 9, 2000June 9, 2000 Decorative window arches finished.  Window and door frames installed.

 

 

 

 

June 2, 2000

June 2, 2000 Exterior wallboard flushed out.  A/C ductwork installed.

 

 

 

 

May 26, 2000

May 26, 2000  Exterior wallboard started.  The great outdoors becomes the great indoors.

 

 

 

 

May 15, 2000

May 15, 2000 Skylight and roof over new reception area framed in, plumbing and electrical roughed in.

 

 

 

 

May 3, 2000

 

May 3, 2000 Second Floor framed and under temporary roof.

 

 

 

 

 

April 29, 2000

 

April 29, 2000 Floor trusses and stairs to second floor installed.

 

 

 

April 20, 2000

 

April 20, 2000  First floor interior wall framing nearly completed.

 

 

 

 

April 14, 2000

 

April 14, 2000  Side wall framing goes up.

 

 

 

 

 

April 10, 2000

 

April 10, 2000  Floor plumbing in and floor poured. Framing starts.

 

 

 

 

 

March 31, 2000

 

March 31, 2000  Foundation built and backfilled.

 

 

 

 

 

March 15, 2000

 

Construction officially began on March 15, 2000 with the digging of the footing.

 

 

 

 

 

 

March 14, 2000   This is what Valley Animal Hospital looked like on the day before construction started.

 

 

 

 

 

Front View on March 14, 2000

 

 

 

 

 

Hit Counter

lightning ballBack To Main Page

 

SITE MAP        Main_Entrance       Home        What's_New       Our_Doctors       Our_Staff       Our_Services       Virtual_Tour       Cool_Links       FYI       Laser       Contact_Us       Wellness       WebCam       Gallery      Whiskers'_Page       Guestbook       Web_Special          Accolades