Valley Animal Hospital after renovation
Our General Contractor

Our Architect

The Designer of Our Rainforest Skylight
The Finished Product, Valley Animal Hospital, October 6, 2000


September 30, 2000 New paving, outside stucco almost finished, new fence installed, most interior details finished. And yes, the skylight is IN!!!!

September 9, 2000 Move completed to new addition. Renovation commences on existing building exterior.

August 11, 2000 Steps and side paving installed. Lots of internal changes. Remodeling starts on the existing building. Now if only that skylight would get here.

July 7, 2000 What a difference. It actually looks like the drawing. External stucco of new addition finished. Windows and doors installled.
June
23, 2000 Stucco base coat almost finished. Color coat started.
Interior drywall hung.
June
16, 2000 Stucco started. Door arches finished. Permanent roof
installed.
June
9, 2000 Decorative window arches finished. Window and door frames installed.

June 2, 2000 Exterior wallboard flushed out. A/C ductwork installed.

May 26, 2000 Exterior wallboard started. The great outdoors becomes the great indoors.

May 15, 2000 Skylight and roof over new reception area framed in, plumbing and electrical roughed in.

May 3, 2000 Second Floor framed and under temporary roof.

April 29, 2000 Floor trusses and stairs to second floor installed.

April 20, 2000 First floor interior wall framing nearly completed.

April 14, 2000 Side wall framing goes up.

April 10, 2000 Floor plumbing in and floor poured. Framing starts.

March 31, 2000 Foundation built and backfilled.

Construction officially began on March 15, 2000 with the digging of the footing.

March 14, 2000 This is what Valley Animal Hospital looked like on the day before construction started.

Front View on March 14, 2000